Peshawar-Karachi Motorway
Project Description
Peshawar-Karachi Motorway (Multan-Sukkur Section)
Length: 392km
Project Name: Peshawar – Karachi Motorway
Project Title (Section): Multan – Sukkur: 392 KM
Karachi – Peshawar Motorway envisages construction / development of 6-Lane access controlled Motorway having total length of 1,100 Km. The proposed Motorway shall be a tolled facility. It shall originate from Karachi through Motorway M-9 (136 Km) up to Hyderabad. From Hyderabad onwards, the proposed alignment shall follow a virgin alignment for 345 Km upto Sukkur. The Sukkur Multan section, 392 Km essentially follows the Left Bank of River Indus.
Type of Road: 06 Lane Access Controlled Motorway
Start Point: Multan
End Point: Sukkar
Responsibility:
Proposing Agency: Ministry of Communications
Implementing Agency: National Highway Authority
Supervising Agency: Ministry of Communications, Government of Pakistan
Location
Province of Punjab and Sindh
Province
Punjab and Sindh
Estimated Cost (US $ Million)
2,889
Executing Company / Sponsors
M/s China State Construction Engineering Corporation
Financing
Government Concessional Loan(GCL)
Supervising Agency
Ministry of Communications, Government of Pakistan
Project Progress Update
Construction works commenced in August, 2016
Contractor mobilized
Multan-Shujabad section inaugurated by Prime Minister on May 2018