The project is located in District Khuzdar in Baluchistan province. The project is construction of 2-lane highway from Basima to Khuzdar. The project length is 110 km.
Location
District Khuzdar in Baluchistan
Province
Balochistan
Estimated Cost (US $ Million)
19.19 Billion Rupee
Executing Company / Sponsors
National Highway Authority
Supervising Agency
Ministry of Communications
Project Progress Update
Feasibility and PC-I completed
PC-I has been approved by ECNEC on 12-04-2017
Procurement of Civil Work is under process
The project Basima Khuzdar has been taken up through PSDP